October 2025 – Trial using mobile phones to track walkers launched
February 2025 – Funicular railway re-opened
August 2023 – Railway taken out of service for repair
January 2023 – Railway re-opened after repairs includes additional infrastructure for summer activities
2023 – Visitor Management Plan review carried out by HIE
2020 – Highlands and Islands Enterprise (HIE) published the Cairngorm Masterplan
September 2018 – Funicular closed due to structural issues with the track.
2001 – Mountain railway opened with access restrictions in place to protect the environment
1998 – WWF and the RSPB initiate a judicial review of the planning consenting process. The court decision concluded that planning consent was valid.
March 1997 – Planning permission was granted, subject to conditions and a legal agreement
August 1994 – A planning application was submitted for construction of a funicular railway on Cairn Gorm mountain
1961 – First chairlift opened in the Cairngorms